Accelerated Bridge Construction (ABC), A Better Approach to Bridge Construction?

Authors

  • Mishal Ahmad Alashari University of Washington, USA

DOI:

https://doi.org/10.31686/ijier.vol4.iss8.577

Keywords:

Prefabricated Bridge, modular structure, precast concrete

Abstract

Accelerated Bridge Construction (ABC) is a common term given to the combination of different procedures that help reduce the construction period of a project.  Utilizing these different procedures on bridge replacement/rehabilitation projects presents several benefits, including reduced traffic congestion and improved on-site safety.  The purpose of this paper is to recognize the difference between Accelerated Bridge Construction and Conventional Bridge Construction, and the process of deciding which approach is more suitable for a particular project.  Specifically, this paper explores the desirable condition in which utilizing ABC would be most beneficial for the owner, builder, community, and environment.  The methodology used in this paper is the content analysis method, which includes a large amount of textual information.  The analytical constructs may be obtained from existing practices, experience, knowledge of experts, and previous research studies.  Throughout this research, data and information was collected from different scientific articles, research papers, books, and journals.  The results conclude that when a project is located in a critical area, and time is a vital factor, the ABC approach can be much more beneficial compared to the conventional approach.  However, this method cannot be applicable unless owners have financial capability, skilled and competent workers, and the required specialized equipment for the job.  Thus, utilizing prefabrication elements is greatly advantageous, but only when owners have the sufficient recourses.

Downloads

Download data is not yet available.

Author Biography

  • Mishal Ahmad Alashari, University of Washington, USA

    Dept. of Construction Management

References

AASHTO - AASHTO Innovation Initiative - Self Propelled Modular Transporters. (n.d.). Retrieved May 22, 2016, from http://aii.transportation.org/Pages/SelfPropelledModularTransporters.aspx

ABC - Accelerated - Technologies and Innovations - Construction - Federal Highway Administration. (n.d.). Retrieved April 24, 2016, from http://www.fhwa.dot.gov/bridge/abc/

An inside look at designing for Accelerated Bridge Construction (ABC) - YouTube. (n.d.). Retrieved June 11, 2016, from https://www.youtube.com/watch?v=YBOczUVZ5lc

Babbie, E. R. (2010). The Basics of Social Research. Cengage Learning. Beam Bridge Construction & Design -Types of Beam Bridges. (n.d.). Retrieved May 22, 2016, from http://www.brighthubengineering.com/structural-engineering/62873-what-are-beam-bridges/

Building Foundation Types for Construction Engineering. (2015, December 22). Retrieved from http://harbun.me/building-foundation-types/

Chapter 18 - Suspension Bridges - Suspension-Bridge.pdf. (n.d.). Retrieved from http://www.ams.ir/jozavat/Shegeftiha/Chapter2/Suspension-Bridge.pdf

Chapter 19 - Cable-Stayed Bridges - ch19.pdf. (n.d.). Retrieved from http://freeit.free.fr/Bridge%20Engineering%20HandBook/ch19.pdf

Design Guide for Precast UHPC Waffle Deck Panel System, including Connections | Federal Highway Administration. (n.d.). Retrieved May 2, 2016, from https://www.fhwa.dot.gov/hfl/partnerships/uhpc/hif13032/chap03.cfm

Framework for Decision-Making - ABC - Accelerated - Technologies and Innovations - Construction - Federal Highway Administration. (n.d.). Retrieved May 22, 2016, from http://www.fhwa.dot.gov/bridge/prefab/frameworkflowchart.cfm

Garver - Engineering, Planning, and Environmental Services. (n.d.). Retrieved from https://garverusa.com/

Home | Federal Highway Administration. (n.d.). Retrieved May 1, 2016, from https://www.fhwa.dot.gov/Insecure Connection. (n.d.). Retrieved May 21, 2016, from https://www.fhwa.dot.gov/bridge/prefab/if09010/report.pdf

Khan, M. A. (2014). Accelerated Bridge Construction: Best Practices and Techniques. Elsevier. DOI: https://doi.org/10.1016/B978-0-12-407224-4.00005-8

Mahmoud, K. (2011). Modern Techniques in Bridge Engineering: Proceedings of 6th New York City Bridge Conference, 25-26 July 2011. CRC Press. Manual 11 Design Of Arch Bridges.pdf. (n.d.). Retrieved from http://ebooks.narotama.ac.id/files/ICE%20Manual%20of%20Bridge%20Engineering%20(2th%20Edition)/Manual%2011%20%20Design%20Of%20Arch%20Bridges.pdf DOI: https://doi.org/10.1201/b11340

Microsoft Word - Snabba brobyten och brobyggnationer_Final_II.docx - SBUF 12691 - Slutrapport Snabba brobyten och brobyggnationer.pdf. (n.d.). Retrieved from http://vpp.sbuf.se/Public/Documents/ProjectDocuments/67DF1791-66C1-426B-8B17-371F122316E7/FinalReport/SBUF%2012691%20-%20Slutrapport%20Snabba%20brobyten%20och%20brobyggnationer.pdf

Nadim, A.-H. (2014, May 28). Jeddah will become a “city of bridges and tunnels.” Retrieved May 26,2016, from http://www.arabnews.com/news/577956

National Building Museum. (n.d.). Retrieved from http://www.nbm.org/

NCHRP. (2011). Application of Accelerated Bridge Construction Connections in Moderate-to-High Seismic Regions. Transportation Research Board.

nchrp20-68a_11-02.pdf. (n.d.). Retrieved from http://onlinepubs.trb.org/onlinepubs/nchrp/docs/nchrp20-68a_11-02.pdf

or11005.pdf. (n.d.). Retrieved from https://library.modot.mo.gov/RDT/reports/TRyy0912/or11005.pdf

Post Tensioning Manual - hif13026.pdf. (n.d.). Retrieved from https://www.fhwa.dot.gov/bridge/construction/pubs/hif13026.pdf

Prefabricated/Precast Bridge Elements and Systems (PBES) for Off-System Bridges - BDK83_977-13_rpt[1].pdf. (n.d.-a). Retrieved from http://www.dot.state.fl.us/structures/structuresresearchcenter/Final%20Reports/BDK83_977-13_rpt[1].pdf

Prefabricated/Precast Bridge Elements and Systems (PBES) for Off-System Bridges - BDK83_977-13_rpt[1].pdf. (n.d.-b). Retrieved from http://www.dot.state.fl.us/structures/structuresresearchcenter/Final%20Reports/BDK83_977-13_rpt[1].pdf

Saudi, G. (n.d.). Traffic in Jeddah is nightmarish to say the least. Retrieved May 26, 2016, from http://ara.tv/gvcsb

Shear connection in composite bridge beams. (n.d.). Retrieved May 2, 2016, from http://www.steelconstruction.info/Shear_connection_in_composite_bridge_beams

SPR-687: Analysis of the State of the Art of Precast Concrete Bridge Substructure Systems - AZ687.pdf. (n.d.). Retrieved from https://apps.azdot.gov/ADOTLibrary/publications/project_reports/PDF/AZ687.pdf

Tang, M.-C. (n.d.). Evolution of Bridge Technology. Retrieved from https://www.researchgate.net/publication/228793919_Evolution_of_Bridge_Technology

The Structure of Scientific Revolutions. (n.d.). Retrieved from http://projektintegracija.pravo.hr/_download/repository/Kuhn_Structure_of_Scientific_Revolutions.pdf

Top 10 Saudi Arabian infrastructure projects. (n.d.). Retrieved May 13, 2016, from https://www.thebig5hub.com/galleries/top-10-saudi-arabian-infrastructure-projects/

truss.pdf. (n.d.). Retrieved from https://www.deldot.gov/archaeology/historic_pres/delaware_bridge_book/pdf/truss.pdf

UHPC-filled duct connections for accelerated bridge construction of RC columns in high seismic zones. (n.d.). Retrieved May 26, 2016, from http://www.sciencedirect.com.offcampus.lib.washington.edu/science/article/pii/S0141029615003351

untitled - LivingBridge.pdf. (n.d.). Retrieved from http://vbn.aau.dk/ws/files/18915659/LivingBridge.pdf

Yamane, T., Tadros, M. K., & Baishya, M. C. (1998). Full Depth Precast, Prestressed Concrete Bridge Deck System. PCI Journal, 43(3), 50–66. http://doi.org/10.15554/pcij.05011998.50.66 DOI: https://doi.org/10.15554/pcij.05011998.50.66

Downloads

Published

2016-08-01

How to Cite

Alashari, M. A. (2016). Accelerated Bridge Construction (ABC), A Better Approach to Bridge Construction?. International Journal for Innovation Education and Research, 4(8), 42-71. https://doi.org/10.31686/ijier.vol4.iss8.577